QCAA General Mathematics Networks and decision mathematics 1

5 sample questions with marking guides and sample answers

Q12
2021
QCAA
Paper 1
1 mark
Q12
1 mark

Which statement is correct?

A

A minimum spanning tree must contain a loop.

B

A minimum spanning tree must contain a cycle.

C

Every network has only one minimum spanning tree.

D

A minimum spanning tree has one more vertex than the number of edges.

Reveal Answer
A

A minimum spanning tree must contain a loop.

By definition, a tree is an acyclic connected graph, meaning it cannot contain any loops or cycles.

B

A minimum spanning tree must contain a cycle.

A fundamental property of any spanning tree is that it connects all vertices without forming any cycles; if a cycle existed, an edge could be removed to reduce weight while maintaining connectivity.

C

Every network has only one minimum spanning tree.

While a network with distinct edge weights has a unique MST, networks with duplicate edge weights can have multiple different spanning trees that share the same minimum total weight.

D

A minimum spanning tree has one more vertex than the number of edges.

Correct Answer

A tree with nn vertices always has exactly n1n-1 edges, so the number of vertices is always one greater than the number of edges.

Q7
2024
QCAA
Paper 1
1 mark
Q7
1 mark

The table shows information for a project with four activities.

ActivityDuration (min)PrerequisiteEarliest starting timeLatest starting time
W104
X200
Y3X22
Z4W, Y55

What is the float time for activity W, in minutes?

A

0

B

1

C

4

D

5

Reveal Answer
A

0

A float of 0 indicates a critical activity where the earliest and latest start times are identical. For activity W, these times differ.

B

1

This value represents the duration of activity W (1 minute), not the available float time.

C

4

Correct Answer

Float time is calculated as the difference between the Latest Starting Time (LST) and the Earliest Starting Time (EST). For activity W, 40=44 - 0 = 4 minutes.

D

5

This value corresponds to the start times for activity Z, rather than the calculated float for activity W.

Q40
2025
VCAA
Paper 1
1 mark
Q40
1 mark

The precedence table below shows the 12 activities required to complete a project. The duration in days and immediate predecessors are shown.

ActivityDurationImmediate predecessors
AA4
BB6AA
CC8AA
DD3AA
EE9BB
FF6CC
GG7B,D,FB, D, F
HH12CC
II6G,HG, H
JJ4E,IE, I
KK3G,HG, H
LL9JJ

The project is to be completed in minimum time.

The float time, in days, of Activity BB is

A

4

B

6

C

8

D

12

Reveal Answer
A

4

This is the earliest start time (EST) of Activity BB, not its float time.

B

6

This is the duration of Activity BB, not its float time.

C

8

Correct Answer

The earliest start time for Activity BB is 4 and its latest finish time is 18. The float time is calculated as Latest Finish Time - Earliest Start Time - Duration, which is 1846=818 - 4 - 6 = 8 days.

D

12

This is the latest start time (LST) of Activity BB, not its float time.

Q8
2023
QCAA
Paper 1
1 mark
Q8
1 mark

Activities P and Q are the critical activities for a project.

ActivityDurationPrerequisite activity
P3
Q6P

What are the earliest starting time (EST) and latest starting time (LST) for Activity Q?

A

3 | 3

B

3 | 6

C

6 | 6

D

6 | 9

Reveal Answer
A

3 | 3

Correct Answer

Activity Q depends on P (duration 3), so its Earliest Start Time (EST) is 3. Since Q is a critical activity, it has zero float, meaning its Latest Start Time (LST) must equal its EST (33).

B

3 | 6

The EST is correct, but the LST is wrong. Because Q is a critical activity, there is no slack, so the Latest Start Time cannot be later than the Earliest Start Time.

C

6 | 6

This incorrectly identifies the EST as 6. Since P starts at 0 and takes 3 units of time, Q can begin at time 3, not 6.

D

6 | 9

Both values are incorrect. The EST is determined by the completion of P (time 3), and since Q is critical, the LST must also be 3.

Q3
2023
QCAA
Paper 1
1 mark
Q3
1 mark

The duration, in minutes, of all activities in a project are shown.

ActivityPQRSTUV
Duration38423234161426

The critical path for the project is PRSV.
What is the earliest completion time for the project if it starts at 11:00 am?

A

12:30 pm

B

1:10 pm

C

1:30 pm

D

2:10 pm

Reveal Answer
A

12:30 pm

This time implies a project duration of 90 minutes. However, the sum of the critical path activities (PRSV) is 38+32+34+26=13038 + 32 + 34 + 26 = 130 minutes.

B

1:10 pm

Correct Answer

The earliest completion time is determined by the total duration of the critical path PRSV. Summing the durations gives 38+32+34+26=13038 + 32 + 34 + 26 = 130 minutes (2 hours and 10 minutes). Adding this to the 11:00 am start time results in 1:10 pm.

C

1:30 pm

This time implies a duration of 150 minutes. The correct duration based on the critical path is 130 minutes.

D

2:10 pm

This time implies a duration of 190 minutes (3 hours and 10 minutes), which is one hour longer than the actual critical path duration of 130 minutes.

Frequently Asked Questions

How many QCAA General Mathematics questions cover Networks and decision mathematics 1?
AusGrader has 105 QCAA General Mathematics questions on Networks and decision mathematics 1, all with instant AI grading and detailed marking feedback.

Ready to practise QCAA General Mathematics?

Get instant AI feedback on past exam questions, aligned to the syllabus

Start Practising Free